Resource Loaded Level of Effort Activities Remaining Late Pushed behind DD and Remaining Early pushed after finsh date

1 reply [Last post]
Pranab Kumar Deb
User offline. Last seen 3 years 26 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 291

All,

I have a resource loaded schedule, where in Level of Effort activities the Remaining late units are pushed behind the DD and Remaining Early Units are pushed after the Finish Date. There is no negative float and no contraint on the schedule, I have also checked that the Calendar's are consistent.

 

Thanks for all help,

 

Pranab

Replies

Zoltan Palffy
User offline. Last seen 5 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

if you use a LOE you have to assign a curve to the resouce for that activity