Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource Loaded Level of Effort Activities Remaining Late Pushed behind DD and Remaining Early pushed after finsh date

1 reply [Last post]
Pranab Kumar Deb
User offline. Last seen 1 year 9 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 285

All,

I have a resource loaded schedule, where in Level of Effort activities the Remaining late units are pushed behind the DD and Remaining Early Units are pushed after the Finish Date. There is no negative float and no contraint on the schedule, I have also checked that the Calendar's are consistent.

 

Thanks for all help,

 

Pranab

Replies

Zoltan Palffy
User offline. Last seen 17 hours 13 min ago. Offline
Joined: 13 Jul 2009
Posts: 2365
Groups: None

if you use a LOE you have to assign a curve to the resouce for that activity