I have a project with common basement and from Ground floor 12 Separate buildings. I have here an option to make all in one project or treat them as separate projects.
The main reason for treating each building a separate projects is as follows
a) If you make one program the total activities will be more than 30,000..and then it will be difficult to manage....
b) Each Buildings will have separate planners & Project Managers to carryout the job..
My question is as follows:
a) If i have given some relation between each project,how does P6 schedule when one of the related project is closed....
b)How to carryout resource levelling for all the 12 projects, which are interrelated with one another, using P6.
c)Is there any other technical difficulties in P6, if you relate different projects,with one another.
Kindly advice......
Replies