Global Change

3 replies [Last post]
Albert Balogo
User offline. Last seen 10 years 34 weeks ago. Offline
Joined: 9 Jun 2008
Posts: 44
Hi Planners,

Do you know how to load the defferent types of resources in P6 using global change into the multiple activity code, like the way we are doing in P3.


Your assistance is highly appreciated

Regards

Albert



Replies

Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Albert,

You are welcome.

Albert Balogo
User offline. Last seen 10 years 34 weeks ago. Offline
Joined: 9 Jun 2008
Posts: 44
Hi Arnold,

Thanks a lot for your advised, that technique is useful.


Regards,

Albert
Arnold Puy
User offline. Last seen 10 years 20 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Albert,

Unfortunately, you can’t allocate resources using global change.

Try to use the easiest way by just filtering your activities using your activity code and select all activities by pressing the shift from your keyboard and select "Assign Resources" located at the right corner of your monitor.

Regards,

Arnold