P6 - Retention of original baseline on progressed acts

2 replies [Last post]
Greg Reichmann
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 5 Jun 2008
Posts: 5
Hi All,

Can anyone please advise on how to change the original baseline of progressed project to match the progressed bars. ie. Start & finish of baseline dates = actual start and finish of progressed activities. Actual dates become new baseline for activities progressed upto the Data Date & new Baseline dates match the current programme on activities not yet started.

Thanks for your help!

Replies

MK TSE
User offline. Last seen 5 years 2 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Further to Ernesto’s proposal, remind to slect the ’new’ baseline in baseline assign/maintain
Ernesto Montales
User offline. Last seen 3 years 19 weeks ago. Offline
Joined: 23 Mar 2002
Posts: 65
Greg,

The easiest way I can think of is make you current programme you baseline that will match everything.


Regards,


Ernesto