Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Original Duration equal to total NOT by level

3 replies [Last post]
Diane Armstrong
User offline. Last seen 16 years 1 week ago. Offline
Joined: 15 Apr 2008
Posts: 10
Groups: None
Using Suretrak 3.0b and we received a project from P3e. The "Original duration" column has the total duration specified at each level. We want to see only that levels duration time.

Can this be changed?

Diane

Replies

Diane Armstrong
User offline. Last seen 16 years 1 week ago. Offline
Joined: 15 Apr 2008
Posts: 10
Groups: None
Ok... I think we solved this one... I filtered all Hammock items and it corrected itself.

Don’t know what Hammock activities are but thats for another lesson ;)

Thanks Diane
Diane Armstrong
User offline. Last seen 16 years 1 week ago. Offline
Joined: 15 Apr 2008
Posts: 10
Groups: None
Hi Dieter... this didn’t change my results except give me a total at the bottom of each level vs. the top.

I may not be explaining this clearly.

Eg. The total project has 463 hours at level 1. But Level 4 also show 463 at each of its jobs although the job doesn’t total 463... it should only show a total of 6.

Hope this explains it better.

Also... i know this is Suretrak but it I don’t see a category for Suretrak and P3 should be fairly simular

Thanks for your assistance
Diane
Dieter Wambach
User offline. Last seen 7 years 4 days ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Diane
Move your mouse into the table area --> right click (or "Format") --> organize --> right side within the window column "Total" --> select top or bottom --> select "Organize now".
This works in P3 and should work in Suretrak as well.
Regards
Dieterr