Progressing and resource loaded activity

1 reply [Last post]
Brian Mitton
User offline. Last seen 10 years 19 weeks ago. Offline
Joined: 27 Feb 2008
Posts: 16
Groups: None
G’day folks,

Your assistence please.

I have loaded an activity with a quantity.

When I progress this activity and insert the actual quantity, I store the performance. On this occasion I am reducing the remaining duration. So when I do this, the actual quantity increases????

How do I fix the actuals and still change the remaing duration?

Thanks.

Brian

Replies

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Brian,

In P6, reducing remaining duration means that you are increasing the "Duration % complete"

So, the easy (!?) answer is that "Recalculate actual units and costs when duration % complete changes" is ticked in the "Calculations" tab at the project level.......