Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Project and Resource calendars

2 replies [Last post]
mike mark
User offline. Last seen 14 years 33 weeks ago. Offline
Joined: 7 Jul 2009
Posts: 10
how does the calendars work individually and together and how they effect man hours and durations in P6.



Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Mike

Whatever software you use if you put a different calendar on a resource to that of the task you will get bizarre results.

If you have the facility tick your resource to follow "calendar as task" and you will have no further problems - even when you change the task calendar.

As Dieter syas - it is all in the manual and help section.

Best regards

Mike Testro
Dieter Wambach
User offline. Last seen 6 years 52 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Mike

Please put questions more specific.
On your installation dvd or cd’s there is a reference manual. There you’ll find all about calendars and resource assignments.

Calendar: Per resource or per activity - a default value per project for new activities.

Assignments: Units depend on duration type, the default per resource, individual entry possible per day or for the hole assignment. Curve is possible. Some parameter settings for the project must be regarded - under tab "Resources" and "Calculations".

Good information on these items you’ll find in the "Help".

Did you consider to join a training?

Good luck!

Dieter