Progress Resources

1 reply [Last post]
Alexandre Azevedo...
User offline. Last seen 16 years 14 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 3
Groups: None
Hi,

I’m trying to calculate the progress of resources on several tasks.
Each task as several resources, and each resource as a different progress.

Does anyone has an idea about how to input the % complete task for each resource independently, and have then a % complete task?

Thank you all for your answers.

Regards
Alexandre

Replies

Arnold Puy
User offline. Last seen 10 years 15 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Alexandre,

Welcome to Planning Planet.

Go to "Assignments" Group them by Resource Name and WBS or Codes then show the "Unit % Complete", "Actual Units" in the column depending on your requirements and manually input the actual units.

If you need to know the % complete for each task then I would suggest to use the Physical % Complete.

Regards,

Arnold