I need Help with P6.2

1 reply [Last post]
Mohamed Saleh
User offline. Last seen 11 years 38 weeks ago. Offline
Joined: 22 Dec 2008
Posts: 7
Hi everybody,
I am facing a problem with Primavera P6.2,i want to copy activities from a project to another,and when i open two projects at the same time i can not switch between them using Ctrl+Tab.If anyone know how to do that please advice.

Replies

Arnold Puy
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mohamed,

When you are trying to open two different projects, you need only CTRL and select the project to open.

When you are trying to view the two projects you don’t need to use the CTRL just simply select the vertical scroll bar and look for the activity to copy and paste it to the other project.

Hope this helps.

Regards,

Arnold