Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

P6; Resource Usage Spreadsheet

2 replies [Last post]
Abeer Mahmoud
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
• During May:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 500hrs
3- remaining units = 600
4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs

• During June:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 1000hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs

• During July:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 0hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs

Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.

Regards,

Abeer

Replies

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Abeer

I have moved this thread to the p6 forum - you will get a better response here.

Best regards

Mike Testro
Abeer Mahmoud
User offline. Last seen 7 years 44 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Dear All,

At P6, Kindly note that if I have a resource code R#1 limit is 42hrs per day this resource was assigned for many activities starting in Mar. and finished in Aug.

And I updated schedule in May 10, 2009

So I need a resource usage spreadsheet showing the following data:
• During May:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 500hrs
3- remaining units = 600
4- Required/downtime units = 1 - (2 + 3) = 1260 - (500 + 600) = -160hrs

• During June:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 1000hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 1000 = 260hrs

• During July:
1- available units (Resource limit per month) = 42hrs per day X 30d = 1260hrs
2- actual units = 0hrs
3- remaining units = 0hrs
4- Required/downtime units = 1 - (2 + 3) = 1260 - 0 = 1260hrs

Regarding that I tried to spreadsheet fields’ customized options but I think I chose a wrong options so If any one have any idea via resource usage spreadsheet or any other report/way please feed me back with steps.


Regards,

Abeer