Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Event Intercepted

10 replies [Last post]
Arnel Lagumbay
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 35
Hi all,

"An Application event has been intercepted pls note the

event code for reference DSECL-0549-E". and after P6

closed.Somebody here encounter this kind of problem?

To those PPp that can share...Thanks in advance..


Regards,
Rnel

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

TONI LUPI

you have lops i your schedule 

Follow steps below to fix the issue:
1. Click F9 to get the Schedule window.
2. Check the Log to file option to save schedule details.
3. Schedule the project.
4. View the log, then fix the loops reported in the log file.

Workaround:

By default P6 only checks 10 loops per schedule.In order to allow more loops in the project, set a PM.ini named MaxLoopsToReportCount under Schedule option and set it value which suits the required loops.  It should not be too much so that schedule will take time to process so many loops.

[Schedule]
MaxLoopsToReportCount=-1 (this setting will show all loops)

Toni Lupu
User offline. Last seen 3 years 10 weeks ago. Offline
Joined: 24 Oct 2006
Posts: 3
Groups: None

Primavera 19.1.2

Error while scheduling

DB : SQL

Error :

an application event has been intercepted. please note the event code for reference 

Event code  : SSFII-0822-6  

What' the explanation ?  How it is affecting the results ?

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

esmaeil fadaei

do not steal someones elses thread create a new post and it will be answered this way others can search for this same problem and the solution.  
esmaeil fadaei
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 17 Dec 2018
Posts: 2
Groups: None

hi all

Primavera 7.0

Error while Removing WBS

DB : SQL

Error :

an application event has been intercepted. please note the event code for reference 

Event code  : DSEIS-2129-2

Zoltan Palffy
User offline. Last seen 3 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Follow steps below to fix the issue:
1. Click F9 to get the Schedule window.
2. Check the Log to file option to save schedule details.
3. Schedule the project.
4. View the log, then fix the loops reported in the log file.

Workaround:

By default P6 only checks 10 loops per schedule.In order to allow more loops in the project, set a PM.ini named MaxLoopsToReportCount under Schedule option and set it value which suits the required loops.  It should not be too much so that schedule will take time to process so many loops.

[Schedule]
MaxLoopsToReportCount=-1 (this setting will show all loops)
Santhosh S
User offline. Last seen 6 years 23 weeks ago. Offline
Joined: 9 Nov 2017
Posts: 2
Groups: None

Primavera 16.2

Error while scheduleing

DB : SQL

Error :

an application event has been intercepted. please note the event code for reference 

Event code  : SSFII-0822-6

 

5182
scheduling_error_16.2.jpg

Montasir Abdelhalim
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 13 Oct 2017
Posts: 5
Groups: None

HI 

Montasir Abdelhalim
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 13 Oct 2017
Posts: 5
Groups: None

HI

 HERE IS THE COPY OF THE MESSAGE OF THE SAME ISSUE: 

 

"*****************************************************

*                EXCEPTION  REPORT                  ******************************************************Date:          13-Oct-17  Executable:    PM.exeApplication:   Primavera Project ManagementEvent Code:    AVAA0-1935-0Message:         Access violation at address 00830C9C in module   'PM.exe'. Read of address 00000008 Context:   1: TfrmMain.actReportsReportsExecute  2: TfrmWizImport.RunCheckInWizard  3: TfrmMain.actCheckIn1Execute  4: TCFormManager.SetToolbar  5: TfrmLogin.FormCreate  6:   7:   8:   9:   10:  Detail:   Type:        EAccessViolation  Object Type: TCUltraButton  Components==========ORI: ORI Win32 #ORI/DB: PMDB,0600.0011.0001.0002IMG: IMG Win32 #1000 System Info===========Username: user   Hostname: USER-PCOS Version: Windows NT ver 6.1, build 7600,  (Intel Pentium)"   PLEASE KINDLY HELP ME TO FIX THIS SO I CAN SEE MY REPORTS. THANKS  MONTASIR
Arnel Lagumbay
User offline. Last seen 11 years 39 weeks ago. Offline
Joined: 31 Aug 2008
Posts: 35
Thanks Dieter,

This happens twice in my P6,but now its working fine.I will note it, if it happens again.


Regards,
Arnel
Dieter Wambach
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Arnel

Within that window you have the choice between three buttons - select "More". Within the following window you’ll get more information --> "Copy" --> paste here.

Or ask Primavera or your local dealer. They should have a reference list for those error codes.

Regards
Dieter