Updating via Importing Data from Another Project

R
R Jones 👤 Member for 20 years 9 months
A
Arnold Puy 👤 Member for 19 years 1 month

Hi R Jones,



First of all, welcome to Planning Planet.



Well, it is not very clear for me however, let me answer your question. But first make a backup to your project.



In order to update your Baseline Resource Quantities, go to Project --> Maintain Baselines and select the Baseline you wanted to update.



Select the "Update" button remove all the checks except for "Update exisitng activities already in the baseline" & "Ignore Last Update Date". In Specify the activities to include: select the "All activities" or filter the folowing activities you want to change.



Then select the "Update Options" radio button, under the "When updating resource assignment data, include:

Mark the checkbox next to "Update existing resource and role assignments" & "Budgeted units and cost" & unselect the rest of the checkbox then ok.



Then select "Update".



You can easily perform this exercise in excel sheet.



HTH.



Regards,



Arnold








Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts