Hello
I have a baseline project which has subsequently had the resources (quantities) updated by a standalone user (i.e. working from a copy of the baseline). Unfortunately the standalone user has also added some new activities and progress.
My problem is I want to update the resource quantities in my baseline but don’t want any of the other updated information.
Is this possible as I have experimented with the Import wizard and also tried via excel but have been unable to import just “Budgeted Labour Units” and “Budget Nonlabour Units”
Apart from having to manually input the data to 8000+ activities does anyone have any suggestions?
Cheers
RB
I have a baseline project which has subsequently had the resources (quantities) updated by a standalone user (i.e. working from a copy of the baseline). Unfortunately the standalone user has also added some new activities and progress.
My problem is I want to update the resource quantities in my baseline but don’t want any of the other updated information.
Is this possible as I have experimented with the Import wizard and also tried via excel but have been unable to import just “Budgeted Labour Units” and “Budget Nonlabour Units”
Apart from having to manually input the data to 8000+ activities does anyone have any suggestions?
Cheers
RB