Change monitoring

2 replies [Last post]
shiv rao
User offline. Last seen 12 years 47 weeks ago. Offline
Joined: 10 Mar 2008
Posts: 62
DEar Guys,
Can any one help me in documenting the changes made by the Contractor from the agreed milestones.

How one should monitor or ask for changes made by the contractor from the previous agreed program / baseline.

One way we are using is my adding a comment in the notebook column tab.
and then printing a report for notebook items for the project.

Regards

SHIV

Replies

Ali Farhat
User offline. Last seen 14 years 51 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
Claim digger is a good tool, but the reports generated are detailed and hard to read (in my opinion) if you have a big number of activities.
my idea, is to maintain and assign the contractors version to your version and create a layout showing variances...you can then filter all the values <> 0
this is primitive but effective to me
António Faria
User offline. Last seen 10 years 8 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 40
Groups: None
Hi

For me, the correct way is always receive a report with the changes made.

In other way, if you receive the updated time schedule in XER format, you can import it and after use the Claim Digger (Primavera\Tools\Claim Digger) to compare.

Other way is showing the baseline and the actual activity in the Gant Chart. There, visually, you can check deviations.