Duration changing with resource changes

1 reply [Last post]
Tom Tom
User offline. Last seen 7 years 8 weeks ago. Offline
Joined: 17 Aug 2014
Posts: 31
Groups: None

Hello All,

     I am having trouble with my project duration changing everytime I change the max units/time of a rersource. What am  I doing wrong. I dont not want a resource to recalculate any of my durations.

Thanks

Replies

Zoltan Palffy
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

go to your project directory

make sure that your project is highlighted and open

look at the defaults setting look at the duration type change it to fixed duration & units. Now when you add new activites the resource will not drive the duraitons.

now you have to fix the duraiton type for the existing activities

go to activities add column

look under General and add Duration Type

change the top one to fixed duration & units then do a fill down for the remainder of the activities

this should fix it.