Actual bar split

3 replies [Last post]
Pacifico Pallasigui
User offline. Last seen 11 years 46 weeks ago. Offline
Joined: 24 Jan 2004
Posts: 62
Groups: None
Planners,

Is it possible to split the Actual bar for example I have an activity Excavation Original Duration = 6 days
during status the activity acquired 90% complete with actual duration 33 = days but in reality it acquired only 6 days . Is it possible to suspend - resume actual activity and the actual bar will be divited to the real situation.

Thanks
Jun

Replies

Oliver Melling
User offline. Last seen 4 years 29 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
I have had people come to me with this problem.

It seems wrong to show a bar from actual start date to actual finish date with no break in it, when it has been suspended and resumed.

This is catered for within P5/6 and is much simpler than creating a task sepcific calendar.

There is a tick box for ’activity non-work intervals’ under the bar-necking tab of the actual bar.
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hello Pacifico,

I know what you mean. You can split the bar by assigning special calendar. let say, from Sep. 1 to 30 there is no activity occur for excavation during these days.

Now, create a new calendar. Select Sep. 1 to 30 as Nonworking days, when done click OK. Assign this calendar to activity "Excavation". To be able to see the necking on the bar, go to View --> Bars --> Bar Setting Tab, Under Bar Necking select "Calendar nonwork time". But prior to mark the checkbox make sure you select "Actual Bar" under timescale.

HTH.

Arnold
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Pacifico,

It is possible to suspend & resume activities with Actual start date. However, it is not possible to make your actual duration become 33 days. It will remain in 6 days or 5.4 days since it is 90% complete. Only the "At Completion Duration" can be extended to 33 or more days even though you will apply the suspend & resume date.

Arnold