Planners,
Is it possible to split the Actual bar for example I have an activity Excavation Original Duration = 6 days
during status the activity acquired 90% complete with actual duration 33 = days but in reality it acquired only 6 days . Is it possible to suspend - resume actual activity and the actual bar will be divited to the real situation.
Thanks
Jun
Is it possible to split the Actual bar for example I have an activity Excavation Original Duration = 6 days
during status the activity acquired 90% complete with actual duration 33 = days but in reality it acquired only 6 days . Is it possible to suspend - resume actual activity and the actual bar will be divited to the real situation.
Thanks
Jun