Difference betn restore & updating baseline in P6

5 replies [Last post]
richu rose
User offline. Last seen 4 days 12 hours ago. Offline
Joined: 13 Feb 2007
Posts: 63
Groups: None
Hi Planners,

What is the difference between restore baseline & update baseline.

Richu

Replies

Khuong Do
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 22 Feb 2010
Posts: 118
Groups: None
Hi, You can understand the difference by reading this post https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-p6/
Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Select the activity

Select the "Status" tab

tick the "Started" box

choose the correct "started" date

tick the "finished" box

choose the correct "finished" date

James Soto
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 12 Jul 2011
Posts: 13
Groups: None

Can you help me? I need to update from 0% to 100 %.

James Soto
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 12 Jul 2011
Posts: 13
Groups: None

How can I update the % complete from 0% to 100 %?

Restore baseline detatches the baseline from the project and restores it as a project. Update baseline updates any changes that have been made to the main project into the selected baseline.