Oracle Primavera - PM6 Member for 15 years 8 months Member for 15 years 8 months Submitted by Khuong Do on Wed, 2016-10-12 07:59 Permalink Hi, You can understand the Hi, You can understand the difference by reading this post https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-… Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Wed, 2011-07-13 15:33 Permalink Select the activity Select Select the activity Select the "Status" tab tick the "Started" box choose the correct "started" date tick the "finished" box choose the correct "finished" date Member for 14 years 3 months Member for 14 years 3 months Submitted by jamessoto on Wed, 2011-07-13 14:33 Permalink Can you help me? I need to Can you help me? I need to update from 0% to 100 %. Member for 14 years 3 months Member for 14 years 3 months Submitted by jamessoto on Wed, 2011-07-13 14:33 Permalink How can I update the % How can I update the % complete from 0% to 100 %? Member for 23 years 11 months Member for 23 years 11 months Submitted by David Forrest on Wed, 2008-06-18 08:51 Permalink RE: Difference betn restore & updating baseline in P6 Restore baseline detatches the baseline from the project and restores it as a project. Update baseline updates any changes that have been made to the main project into the selected baseline. Log in or register to post comments
Member for 15 years 8 months Member for 15 years 8 months Submitted by Khuong Do on Wed, 2016-10-12 07:59 Permalink Hi, You can understand the Hi, You can understand the difference by reading this post https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-…
Member for 16 years 7 months Member for 16 years 7 months Submitted by Gary Whitehead on Wed, 2011-07-13 15:33 Permalink Select the activity Select Select the activity Select the "Status" tab tick the "Started" box choose the correct "started" date tick the "finished" box choose the correct "finished" date
Member for 14 years 3 months Member for 14 years 3 months Submitted by jamessoto on Wed, 2011-07-13 14:33 Permalink Can you help me? I need to Can you help me? I need to update from 0% to 100 %.
Member for 14 years 3 months Member for 14 years 3 months Submitted by jamessoto on Wed, 2011-07-13 14:33 Permalink How can I update the % How can I update the % complete from 0% to 100 %?
Member for 23 years 11 months Member for 23 years 11 months Submitted by David Forrest on Wed, 2008-06-18 08:51 Permalink RE: Difference betn restore & updating baseline in P6 Restore baseline detatches the baseline from the project and restores it as a project. Update baseline updates any changes that have been made to the main project into the selected baseline.
Member for
15 years 8 monthsHi, You can understand the
Hi,
You can understand the difference by reading this post https://doduykhuong.com/2016/09/06/how-to-update-baseline-in-primavera-…
Member for
16 years 7 monthsSelect the activity Select
Select the activity
Select the "Status" tab
tick the "Started" box
choose the correct "started" date
tick the "finished" box
choose the correct "finished" date
Member for
14 years 3 monthsCan you help me? I need to
Can you help me? I need to update from 0% to 100 %.
Member for
14 years 3 monthsHow can I update the %
How can I update the % complete from 0% to 100 %?
Member for
23 years 11 monthsRE: Difference betn restore & updating baseline in P6
Restore baseline detatches the baseline from the project and restores it as a project. Update baseline updates any changes that have been made to the main project into the selected baseline.