Difference betn restore & updating baseline in P6

Member for

16 years 7 months

Select the activity

Select the "Status" tab

tick the "Started" box

choose the correct "started" date

tick the "finished" box

choose the correct "finished" date

Member for

14 years 3 months

Can you help me? I need to update from 0% to 100 %.

Member for

14 years 3 months

How can I update the % complete from 0% to 100 %?

Member for

23 years 11 months

Restore baseline detatches the baseline from the project and restores it as a project. Update baseline updates any changes that have been made to the main project into the selected baseline.