Adding New Activity in restored Baseline then Assigning it into Progressed Schedule

1 reply [Last post]
Muhammad Bilal
User offline. Last seen 4 years 42 weeks ago. Offline
Joined: 9 Apr 2015
Posts: 14
Groups: None
All Members Good Day.  I am facing one problem which is i made Rev-05 of my In-Progress Project in which i added one Activity given Relationships to some other activities. I made the Rev-05 by Restoring the Baseline. Now when i assigned this Latest Baseline to Updated Progressed Schedule, the added new Activity is not shown. Please let me help out. How can i Show effectively the added activity in the new baseline with Actual Progress Schedule. Thanks

Replies

Arun Balakrishnan
User offline. Last seen 7 years 49 weeks ago. Offline
Joined: 6 Sep 2015
Posts: 2
Groups: None

I also face the same probelm,

I solve the issue by adding the same activity, link and same activity ID  in Actual progress Schedule.