Early / Late Remaining Units Report

1 reply [Last post]
S Harding
User offline. Last seen 16 years 2 weeks ago. Offline
Joined: 1 Apr 2008
Posts: 5
My construction activities of an Eng. / Proc. / Const. schedule do not start until June 9th and my data date is May 19th.

I am running a report for (resources) Early / Late Dates sorted by cost code. Some of my late dates in the report are showing as early as March 17th.

Why would my late dates be showing up that early in the project; even though the earliest dates for that particular cost code in the schedule are not scheduled to start until late June.

I am using Early / Late Remaining Units.

Replies

Ian Adan
User offline. Last seen 14 years 22 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 6
... Check for negative float.