Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Reamaining early cost and Remaining late cost - Calculation logic

1 reply [Last post]
BALAJI VK
User offline. Last seen 7 years 8 weeks ago. Offline
Joined: 2 Oct 2010
Posts: 7
Groups: None

 

Hi,

 

Can anyone please explain me how the "Reamaining Early cost" and "Remaining Late cost" are being calculated?

 

Generally, What is the logic behind this calculation?

 

Regards,

V.K.Balaji

Replies

Mike Testro
User offline. Last seen 1 week 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi VK

The principle is very simple:

The first ninety percent of the work takes the first 90% of the cost.

The last 10% of the work takes the last 90% of the cost.

Best regards

Mike Testro