My construction activities of an Eng. / Proc. / Const. schedule do not start until June 9th and my data date is May 19th.
I am running a report for (resources) Early / Late Dates sorted by cost code. Some of my late dates in the report are showing as early as March 17th.
Why would my late dates be showing up that early in the project; even though the earliest dates for that particular cost code in the schedule are not scheduled to start until late June.
I am using Early / Late Remaining Units.
I am running a report for (resources) Early / Late Dates sorted by cost code. Some of my late dates in the report are showing as early as March 17th.
Why would my late dates be showing up that early in the project; even though the earliest dates for that particular cost code in the schedule are not scheduled to start until late June.
I am using Early / Late Remaining Units.