URGENT PLEASE!

3 replies [Last post]
rabbani wgl
User offline. Last seen 15 years 45 weeks ago. Offline
Joined: 9 May 2006
Posts: 15
Groups: None
Dear Experts,

How to change the Late Start & Late Finish dates in the schedules, as it shos some funny 3 years back daes. Please advsie ASAP. Thanks

Replies

Andrew Dick
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 295
Don’t forget to check for External Dates, These dates are applied in a fashion similar to constraints, but are derived from external links to other projects.

I’ve found a heap of them in the ones I’ve been looking after, it appears they came from excessive copy and pasting of the schedule in an attempt to create backups and copies in case the network crumped.

Imagine the look on their eyes when they learnt about the baseline feature????????

Anyway they can cause a headache.

Andy
ian adan
User offline. Last seen 16 years 37 weeks ago. Offline
Joined: 25 Jan 2006
Posts: 5
If your early dates are as expected then check your TF column. Looks like you have a constraint date which is giving you 3 years negative float.
Ashraf Jahangeer
User offline. Last seen 8 years 3 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Dear Rabbani,

Check the data date for the project, predecessor and successor of the activity in question.

Regards,

Ashraf