Urgent Help Please
EVERY activity in the schedule MUST have a successor except the last one.
For Schedule % Percent completion, Check following
1. Make sure your data date is valid
2. Your baseline must be assigned.
However, for WBS, cost must be assigned to activites.
Check above points and schedule again by pressing F9.
For Schedule % Percent completion, Check following
1. Make sure your data date is valid
2. Your baseline must be assigned.
However, for WBS, cost must be assigned to activites.
Check above points and schedule again by pressing F9.
dud you update teh schedule ?
if you did update it what % complete type are you using ?
did you change the data date ?