Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Urgent Help Please

7 replies [Last post]
adab azeez
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
While scheduling my project, my schedule % complete value increases for few seconds on the screen and later it adopts the previous constant value. I mean my schedule % complete value is not changing. Any leads please?

Replies

Zoltan Palffy
User offline. Last seen 3 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

EVERY activity in the schedule MUST have a successor except the last one. 

adab azeez
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
I guess I have fixed it now. For this I have taken the following three actions. Probably anyone of these three actions have brought me on the right track. 1. I reduce the price per unit of each resources to 1$/ unit. 2. Many of the equipments' last activities were not having successor . So I assigned a successor. 3. All of the equipment's first activity were sharing same predecessor despite of having internal links between them. So removed all the predecessor except few leading equipments. May anyone of the above worked for me. Thank you so much for your support.
Sultan Salabat
User offline. Last seen 5 years 2 days ago. Offline
Joined: 4 Apr 2017
Posts: 3
Groups: None

For Schedule % Percent completion, Check following

1. Make sure your data date is valid

2. Your baseline must be assigned. 

However, for WBS, cost must be assigned to activites.

Check above points and schedule again by pressing F9.

Sultan Salabat
User offline. Last seen 5 years 2 days ago. Offline
Joined: 4 Apr 2017
Posts: 3
Groups: None

For Schedule % Percent completion, Check following

1. Make sure your data date is valid

2. Your baseline must be assigned. 

However, for WBS, cost must be assigned to activites.

Check above points and schedule again by pressing F9.

adab azeez
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
Yes I change the data date.
adab azeez
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 19 Jul 2016
Posts: 50
I am using duration type.
Zoltan Palffy
User offline. Last seen 3 days 17 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

dud you update teh schedule ?

if you did update it what % complete type are you using ?

did you change the data date ?