Primavera P 5.0 schedule problem

1 reply [Last post]
Bilal Mohammed
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 4 Jan 2007
Posts: 8
Groups: None
Hello Friends

Im new to Primavera P5.0. I have a problem when scheduling the project. The Early start dates of completed activities are also updated with in progress activities. I am producing reports in the layout itself. So I dont want the Early start column to be updated for completed activities. I hope somebody will have the solution. Thanx in Advance

with lots of love
Bill

Replies

Kevin Button
User offline. Last seen 2 years 19 weeks ago. Offline
Joined: 16 Jul 2003
Posts: 112
Groups: None
Hi

Instead of using the Early Start column, try using Start instead. This will show the activity Early Start date until it has started, then will show the Actual Start date.

HTH