Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera P 5.0 schedule problem

2 replies [Last post]
Bilal Mohammed
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 4 Jan 2007
Posts: 8
Groups: None
Hello Friends

Im new to Primavera P5.0. I have a problem when scheduling the project. The Early start dates of completed activities are also updated with in progress activities. I am producing reports in the layout itself. So I dont want the Early start column to be updated for completed activities. I hope somebody will have the solution. Thanx in Advance

with lots of love
Bill

Replies

Bilal Mohammed
User offline. Last seen 12 years 48 weeks ago. Offline
Joined: 4 Jan 2007
Posts: 8
Groups: None
Hi mktse

Thanx for ur reply. But for the solution, if i give start and finish for ES & EF, then the columns will be updated with actual start and actual finish
MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Your post is better on forum "Primavera Enterprise - Teamplay / P3e & P3ec" since P5.0 is under that category.