Im new to Primavera P5.0. I have a problem when scheduling the project. The Early start dates of completed activities are also updated with in progress activities. I am producing reports in the layout itself. So I dont want the Early start column to be updated for completed activities. I hope somebody will have the solution. Thanx in Advance
with lots of love
Bill
Im new to Primavera P5.0. I have a problem when scheduling the project. The Early start dates of completed activities are also updated with in progress activities. I am producing reports in the layout itself. So I dont want the Early start column to be updated for completed activities. I hope somebody will have the solution. Thanx in Advance