How to show critical Path for an updated activitie

5 replies [Last post]
Haresh Jayanth
User offline. Last seen 1 year 2 weeks ago. Offline
Joined: 24 Aug 2006
Points: 215
Hi Guys,

How to show critical path for an updated activites / already completed activities , when the project is in progress. to make my question clear i will given one example

Example

The substructure in a project is already completed. The balance is superstructure of the building. if i choose longest path it show critical path on balance activities ? My question is that how can i show critical path for activites which is already completed i.e. substructure as per the present progress of the site? Since the critical path may not be same when the critical activities are progressing ahead of schedule. in this case if i want to show critical path on already completed activites? How can i show it?

Replies

Sooraj G Othayoth
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 29 Dec 2004
Points: 18
Hi Alex,
thanks for the help.
On the expert help, can I get anything on the internet?
Regards
Alex Wong
User offline. Last seen 8 weeks 4 days ago. Offline
Joined: 12 Feb 2003
Points: 874
Hi

As Ronald said this is what we call "As-built Critical Path" and it is a expertise on its own.

You may need to re-create the entire schedule base on its original logic and then unschedule all the AS AF and reschedule the plan base on its durations.... this is a long process and require a lot of other skill other than planning.

If the As Build CP is a claim related issue then better refer to the experts

Good Luck

Alex
Sooraj G Othayoth
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 29 Dec 2004
Points: 18
Hi moderator,
Can we shift this thread to contract & claims management since it is more related to that forum.
regards
sooraj
Sooraj G Othayoth
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 29 Dec 2004
Points: 18
Hi Ronald,
Can you please elaborate on how to arrive at the longest path from the updated program.
Can anyone suggest any links which can help me in finding more about as built critical path?
cheers
sooraj
Ronald Winter
User offline. Last seen 1 hour 9 min ago. Offline
Joined: 4 Jan 2003
Points: 891
Haresh,

What you are asking for is the “As-Built Critical Path.” P5 is unequipped to display this. This is not a built-in function. There is one add-on software company that sells software for this.

Forensic Experts make a living out of identifying these As-Built Critical Path activities. It takes a lot of experience and knowledge of CPM to do this (hence, that is why they are called “experts.”) The AACEi sponsors a group dedicated to CPM forensic science (in fact, I believe that they are introducing a certification for this practice at next year’s conference.)

I know that I didn’t give you the answer that you wanted, but at least I hope that I gave you some ideas about the correct courses of action. Good luck!

Market Place

We want to build software that solves real problems, allow people to work more productive and happier.
The book is designed for users of earlier versions to upgrade their skills and for new planners to learn the software.
A user guide and training manual written for professionals who wish to learn how to plan and control projects in an established Primavera Enterprise environment with or without Resources & Roles.
A comprehensive product suite with the flexibility to meet the varying needs of everyone involved in running projects
The toolkit provides advanced analytical tools which can help identify areas of poor schedule quality at the click of a button.