Force to show critical task

N
Neal Walsh 👤 Member for 18 years 8 months

Yusuke,



F9, Options.....



Make sure that under the ’Define Critical Activities’ it is set to 0 days, and not a negative figure, as this will eliminate Activities with 0 days Total Float from the Critical Path.



Walshy

B
Balaji Surendiran 👤 Member for 22 years

To make an activity critical either you need to play with the relationaships or apply contraints(not a right way of making a activity critical)...



regards

Balaji

A
Anoon Iimos 👤 Member for 19 years 8 months

Yusuke,



Though your schedule might not show it as critical, the activity ("install scaffold") is really necessary and practically critical (or is it not?).



There are several ways to do it, but I supposed if you had arranged or organized your activities practically, for sure it will show as critical, please check the logic links.



cheers


G
Gary Whitehead 👤 Member for 17 years 2 months

why would you want to show it as critical when it isn’t?



Free Float has nothing to do with criticality -it is only Total Float that defines the critical path.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts