Hi,
Im using P6.2, I have a task named "INSTALL SCAFFOLDS" having a FREE FLOAT of 0 day and a TOTAL FLOAT of 30 days. It is not being shown as critical but I want to show it as as a critical task, how to force it to show as a critical task? I have other tasks having a FREE FLOAT of more than 0 days and a TOTAL FLOAT of 20 days but I dont want them to show a critical, only the task named "INSTALL SCAFFOLDS".
Psl advise. Thanks!
Im using P6.2, I have a task named "INSTALL SCAFFOLDS" having a FREE FLOAT of 0 day and a TOTAL FLOAT of 30 days. It is not being shown as critical but I want to show it as as a critical task, how to force it to show as a critical task? I have other tasks having a FREE FLOAT of more than 0 days and a TOTAL FLOAT of 20 days but I dont want them to show a critical, only the task named "INSTALL SCAFFOLDS".
Psl advise. Thanks!