Any Diff. b/w longest pat & total float equals to 0

4 replies [Last post]
Shah. HB
User offline. Last seen 18 weeks 5 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Is there any diff between total float EQ 0
and
Longest path EQ Yes in filter option

Is there any thing like during updating we use longest path option, for baseline without updates we use total float option ?

Replies

Shah. HB
User offline. Last seen 18 weeks 5 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Many thanks Mr.Raviraj
A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Or at best, u can drop a mail / PP to Ron Winter. He has submitted one very good paper on "Longest Path V/s Critical Path" few years before.

I dont have it now, but thats the best stuff, i got till date on this issue.

Cheers,

Rav
A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Yes, there is a difference

Check the link below

http://scheduleanalyzer.com/sa_long_theory.htm