Activity Codes

10 replies [Last post]
Milton Maindonald
User offline. Last seen 14 years 11 weeks ago. Offline
Joined: 12 Jul 2007
Posts: 17
Groups: None
When I copy and paste an activity the codes disappear.
I have also discovered that when I copy and paste an entire Project the area codes are missing.

I have also installed service pac 4 to no avail.

I am using Release 5 SP4.

Has anyone got some ideas on how to remedy this???

Replies

Juan Dela Cruz
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 7 Dec 2007
Posts: 13
Hi Dieter & Milton.

Thanks, it worked!
Unchecking the "secure tick box" enables P5 file to be copy/paste without losing the activity codes.

More Power and regards.
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Juan
I just checked and found the same. So secure activity codes are excludes when you use Copy-command.
You can access it by: Enterprise --> Activity Codes --> select "Global" --> button "Modify" --> switch off "secure-code" box for this code.
Regards
Dieter
Juan Dela Cruz
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 7 Dec 2007
Posts: 13
Hi Milton,

Thanks for your reply.

However, how would I know my activity codes are secure? (Where could I find the "secure tick box"?)
I’m using Primavera Project Mgt Release 5.

Regards,
JDLC
Milton Maindonald
User offline. Last seen 14 years 11 weeks ago. Offline
Joined: 12 Jul 2007
Posts: 17
Groups: None
Morning Juan,

I discovered that I had activated the "Secure Code" in some of my Area Codes, and when we do that non of the codes within the specific project copy or export. I removed the tick in the "Secure Code" box and bingo, All ok.

Thanks for getting in touch.

You may want to check your codes to se that non of them are selected as "Secure".

Cheers,

Milton.
Juan Dela Cruz
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 7 Dec 2007
Posts: 13
Yes I tried XER and the codes are missing.

As an alternative solution,

How can I use Global Change to restore the Activity Codes in my latest Project File? I mean, the latest file has been already updated (durations and relationships) except the Activity Codes which I need to restore. The original file which has Activity Codes is still available.
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Juan
Sorry, I never had this situation.
Just for check: Did you try to export this project to an XER-file? Then open XER with an editor and check if the code-assignments are still there.
If not, IT should check the database - MS-SQL?
Good luck
Dieter
Juan Dela Cruz
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 7 Dec 2007
Posts: 13
Hi Dieter,

I’d say, GLOBAL activity codes.


Thanks so much for your time.
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Juan
Which type of activity codes: Global, EPS (not copied in P5), or Project?
Dieter
Juan Dela Cruz
User offline. Last seen 8 years 37 weeks ago. Offline
Joined: 7 Dec 2007
Posts: 13
I am in the same situation.
I’m using Primavera 5.0 SP1. I lost the assigned activity codes, when I copied a project and paste it to a different EPS. Previously the procedure works OK (the codes are still there), but recently i noticed that my copies (i copy project to create back-ups) don’t have the previously assigned activity codes. I had made sure that I’ve checked the "include activity codes" in the dialog box during the copy/paste action.

1. How shall I copy a project and retain assigned codes?
2. How shall I retain activity codes to the back-up files?

THanks for the help.

Cheers!
Dieter Wambach
User offline. Last seen 7 years 1 week ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Milton
This is P3e - not P3. When you copy an activity, I know two chances to loose a code:
1. After you click on "paste", a window will appear where you can mark, which items to be copied as well.
2. You grouped by a code. Then you paste into an area where no code is assigned.

Projects: In P5 EPS-activity-codes are not copied together with the project - solved in P6.

Regards
Dieter