Order of Activity Codes

1 reply [Last post]
Jonathan Ward
User offline. Last seen 12 years 16 weeks ago. Offline
Joined: 23 Jan 2007
Posts: 114
Hello,
i have noticed that the Order Column within Activity Codes has a maximum entry count of 254 ( i assume this is because of P3 being a 16 bit program). is there any method of making the Order filed alphnumeric or any other method of forcing the Order Filed to take more than 254 entries?
as always,, many thanks
Jon

Replies

Bijaya Bajracharya
User offline. Last seen 8 years 1 week ago. Offline
Joined: 25 Feb 2005
Posts: 175
Groups: None
If you don’t use any order number at all, the codes will be sorted alphanumerically.

So the solution is to make your activity code including a rank number.