Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Actual % Completion vs. Planned % Completion

12 replies [Last post]
Basel Al-Jazzar
User offline. Last seen 12 years 34 weeks ago. Offline
Joined: 14 Sep 2003
Posts: 18
Groups: None
how an i disconnect the actual % completion for each activity from the actual duration - in other way, to feed the % completion manually and not to be related the actual duration of the activity ? and how can i show the planned % completion for each activity linked with the planned early start of each activity ?

Replies

Hassan Emam
User offline. Last seen 16 years 47 weeks ago. Offline
Joined: 20 Dec 2006
Posts: 18
Groups: None
what actually i need to do is plot a graph showing the relations between time and % completed
the percentage completed will be of Early planned, Late planned and Actual % Completed so from this graph you can know where are you from Schedule (Behind or Ahead or in between) Got my Point???
Edgar Ariete
User offline. Last seen 5 years 26 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
Hassan,

Yes you can. If you planned it late. Just make two (2) targets. One early target and one late target (just make sure you can get approval for your late target).

this is free anyway...
Hassan Emam
User offline. Last seen 16 years 47 weeks ago. Offline
Joined: 20 Dec 2006
Posts: 18
Groups: None
Edgar,

Thanks for your interest and considering my query. I know what you are saying is correct but can i update a target project (Automatic Update) by late dates. that is my original question. if i updated the progress automatically it will update according to the early dates can i do the same proccess by using late dates
Edgar Ariete
User offline. Last seen 5 years 26 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
Hassan,

You can make as many target project as you like, but actuals are actuals. You can never have two actual start or actual finish for the same activity at the same time.

Updating Target is realizing your plan. Modeling it as if it actually happened.

Then compare it with your current project (which is your actual one), a dynamic project that reflects your actual resources and performance.

hope this explains my view...
Hassan Emam
User offline. Last seen 16 years 47 weeks ago. Offline
Joined: 20 Dec 2006
Posts: 18
Groups: None
Edgar Ariete
thank you for your consideration but i think you didn’t get my point. i want the late dates % complete planned and the early as well to compare it to the actualsand know what is the exact situation. If we make all the activities with TF=0 then we don’t have early and late dates i need to plot a graph containing % Complete Early planned, % complete Late Planned and % Complete Actual Vs. The project duration in month. I hope you got my point and everyone can help me.


Regards,
Hassan Emam
Edgar Ariete
User offline. Last seen 5 years 26 weeks ago. Offline
Joined: 17 Jul 2005
Posts: 184
i guess nobody is planning to be late! just in case, make all your activities critical (in target project), that means zero total float for all the activities! and update it..

i hope it works
Hassan Emam
User offline. Last seen 16 years 47 weeks ago. Offline
Joined: 20 Dec 2006
Posts: 18
Groups: None
well...
the planned progress as you are discussing is the early planned % complete
and the actual planned % Complete we can get it from the current project by using the actual % completed in it
how can we get the late planned % complete

actualy actualy what i want to do is to make a graph where the horizontal scale will be time by month
the vertical scale will be %
then i’ll want to draw the early and late % VS time and each month update the actual if the actual line falls above the early planned that means we are ahead of schedule if falls between the two lines that means we still can finish on time
and finally if the actual line falls under the late planned line that means that we are behind schedule
so my problem now how to get the late planned %
Can you help me with this

Regards,
Hassan Emam
ulysses garcia
User offline. Last seen 13 years 8 weeks ago. Offline
Joined: 22 Aug 2005
Posts: 259
Groups: GPC Qatar
Hi

Target % will only show if you copy your schedule as target then compare it to the current schedule update as of D.D.( data date).. Menu..Tools > look for target in sub menu...
Mohamed Basheer
User offline. Last seen 5 years 28 weeks ago. Offline
Joined: 1 Apr 2004
Posts: 22
Groups: None
Mr. Basel

Planned Progress will come only if you have a Target assigned and Update the target programme through update progress as on data date.( No manual work)

Hope i am right.

Regards
Yembee
Basel Al-Jazzar
User offline. Last seen 12 years 34 weeks ago. Offline
Joined: 14 Sep 2003
Posts: 18
Groups: None
thanx for reply, when u uncheck the first time this will lead that i have to fee actual % completion manually. But what about target % completion ? shall i feed it manually then ??
Ronald Winter
User offline. Last seen 3 years 2 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
This is Autocost Rule #1. Select Tools / Options / Autocost Rules. The Un-check the first rule, "Link remaining duration and scheudle percent complete." Good luck!
Santhosh kumar Na...
User offline. Last seen 6 years 14 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 66
for actual progress u will be puting manually right? for planned % progrss make a copy of ur target auot up date that u and see % complete. to auto update go to tools, update progress, (Check for all activity)