Early Start vs. Actual Start in P3.1

4 replies [Last post]
Ruel Camaquin
User offline. Last seen 3 years 31 weeks ago. Offline
Joined: 16 Nov 2008
Posts: 100
Guys,

Just like to know why is the EARLY START dates also changes to the actual start dates everytime i encode the ACTUAL START date? Is there a trick or method to make the EARLY dates fixed to the target dates. Thanks in advance for the early response.

Cheers & Regard.

Replies

Ruel Camaquin
User offline. Last seen 3 years 31 weeks ago. Offline
Joined: 16 Nov 2008
Posts: 100
It is a very big help! i’ve even added variance column, now i can see me delays and ahead in my schedule.

Thank you so much.
Ferdinand U.
User offline. Last seen 6 years 33 weeks ago. Offline
Joined: 19 Jul 2007
Posts: 142
add target1 early start and target1 early finish column
Ruel Camaquin
User offline. Last seen 3 years 31 weeks ago. Offline
Joined: 16 Nov 2008
Posts: 100
I aleady have a target schedule. The only thing is that everytime i encode the actual start and finish dates, the early start column dates also changes to the actual dates i encoded. Ex. masonry works early start is 10NOV08 as the target, then i encoded 15NOV08 as an actual start for masonry works - after i clicked the ok button, the early start date for the target also changes to the actual start date of 15NOV08A although the bar chart does not move.

I cannot compare the early start and the actual start with just the bar charts alone, i need to have the early start dates same as the target reference against the actual start.
Anoon Iimos
User offline. Last seen 2 years 13 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
make a target, so that it become fixed.