Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Resource relationship within a task

6 replies [Last post]
Redzuan Samsudin
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 27 Jun 2006
Posts: 11
Good day to all

It was a relief that I found this forum!!! It is very helpful. Thank you all for your contribution.

My questions is:
Can we link many resources for a single task. Example:
Task = Install & Check Pipe Spool.
Resource use = Rigger, Pipe Fitter, Pipe Welder, Firewatcher, NDT
My guery = Can we link above resources in the task. Rigger SS Pipe Fitter FF Pipe Fitter FS NDT.

Hope you all understand my question.

Thanks & regards.

Replies

Redzuan Samsudin
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 27 Jun 2006
Posts: 11
Good day

Thanks for info.
I will check & dload their demo.

Thanks again.

Redzuan
Dayanidhi Dhandapany
User offline. Last seen 3 years 4 weeks ago. Offline
Joined: 18 Mar 2003
Posts: 470
Groups: None
Primavera is task based, so you can’t show linking relationship for resources in P3. you can think of Spider Project Software for that option. you can find a demo copy from their website.
Redzuan Samsudin
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 27 Jun 2006
Posts: 11
Good day

Thanks for the input.

So, the solution you mention is the ONLY way to link resources within a task??

My post/question arises because during my presentation to my boses (yesterday), one of them mentioned that linking resources in an activity is possible --> to achieve a logical Manning Level.

The way he said it, its like linking task by using relationship line.

Is this possible?

Thanks
Sunley Mathew, PMP
User offline. Last seen 3 years 9 weeks ago. Offline
Joined: 5 Sep 2003
Posts: 18
Groups: GPC Qatar
Hi Redzuan Samsudin ,
In Primavera Project Planner P3 we have an option in the Resource window(used for adding resource to task),for Resource Lag & Resource Duraton.By the proper use & adjustment of these you can for eg. have one resource at the start of a task, another at the end etc.
Rashid Iqbal
User offline. Last seen 17 years 3 weeks ago. Offline
Joined: 3 May 2005
Posts: 94
Groups: None
Hi,

Would not recommend, however, the thing which are looking for can be managed easily if you make resources as activties and then link them as you want. You can certainly make a hammock to umbrella these activities/resources.

Regards
Rashid
Vahid Barzegar
User offline. Last seen 15 years 33 weeks ago. Offline
Joined: 10 Sep 2005
Posts: 2
Hi Redzuan Samsudin,

In P3 you can choose a task as "Independent" which based on resources. I think, it is a way to solve your problem.