hammok activity update

5 replies [Last post]
Forum Guest
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 28 Jan 2009
Posts: 1
Groups: None
when i whant update hammok activity in p3 , "cost this period" are negative .
I whant some information about update hammok activity

Replies

Eric Chou
User offline. Last seen 41 weeks 2 days ago. Offline
Joined: 19 Jul 2004
Posts: 29
Groups: None
Attached is the write-up by myself regarding Hammock Activities. Please review for your reference.

Go to the
http://www.htcprojectcontrols.com/TTB2004-6.pdf

Eric Chou, PE
HTC Project Controls, Inc.
Luca Basile
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Why You do not use Wbs activities?
The hammock is just considering the first with the s-s relat. and the end with f-f relationship, in a chain.
If any activity in the middle of the chian is going out of the originally first and last teh hammock is not covering it any more. Or You have to chekc every update time.
With Wbs just put it and define the level must summarize.
Much more easier. If your purpose is just summarize a group of activities.
rahil khan
User offline. Last seen 19 years 41 weeks ago. Offline
Joined: 10 May 2004
Posts: 7
since hammocks are attached to the earliest start date and the latest finsh dates, any updates will automatically will be incorporated
Luca Basile
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 10 Jul 2003
Posts: 288
Groups: TILOS
Hammock should be update automatically by P3.
As per instruction given in the manual for summarizing activities.
You should not need to update them, as well as the wbs activities.
MK TSE
User offline. Last seen 3 years 47 weeks ago. Offline
Joined: 27 Feb 2002
Posts: 550
Groups: None
Which field you are updating in Hammock?