Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Conversion of Manhours into Durations

12 replies [Last post]
Muhammad Bilal
User offline. Last seen 4 years 42 weeks ago. Offline
Joined: 9 Apr 2015
Posts: 14
Groups: None
Dear Sirs/fellows, I have standard manhours per unit of electrical activities. such as installation of MCC panel, Cabling works having values in decimals and/or small manhours. means per meter cabling manhours. 1 panel installation manhours. so how could i use this to calculate the activity duration???

Replies

Melih Keskintas
User offline. Last seen 5 years 16 weeks ago. Offline
Joined: 14 Sep 2018
Posts: 6
Groups: None

There are two ways to do this. Firstly, you may determine your crew size and then you may calculate the duration based on the man hour you have assigned. Secondy way is to determine the duration of the activity and estimate your crew size. Second method can be used if your activitiy is not on the critical path. If your activiy is on critical path, you have to determine your crew size according to the duration. In both situations, you need to take into consideration the max. crew size that can work on the specific activity in order not to decrease the productivity at the construction site.

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

divide the manhours per actiivity by the number of men you want to use to do that task 

example power panel installation is 48 hours

so using 1 man per day 48 hours / 1 man @ 8 hours =6 days duration

using 2 men per day 48 hours / 2 men per day is 16 hours = 3 days duration

so 48/8=6 days for 1 man

or  48/16= 3days for 2 men 

Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Realistically, it is not too much. In fact it is not even enough when you're pulling bigger cables and longer lengths. Copper cables are delicate, so you don't need too much force, but just a steady and moderate rhythm of pulling. It would be easy if you're just going on a straight line. Curves and perpendiculars are quite difficult.
Rafael Davila
User offline. Last seen 10 hours 8 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
  • By the same token it might be that going from 4 workers to 6 workers pulling cables on same conduit it is too much. 
  • At times such extreme examples are good as to make the point on how such simplified model can be so wrong.
  • Only in very few cases and within certain range that it makes sense.  If the functionality does not provide to prevent falling outside the range you might be better off if not using it at all. 
  • Most of the abuse of such linear assumption probably happens not in the obvious extremes but in the frequency wrong assumption is used. 
Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
However, going realistic and economical perhaps have no room for trial and error, so you need to think straightforward and practical. No need to put 100 men to lay 100 blocks at once. Imagine the chaos, and the wall may never stand.
Rafael Davila
User offline. Last seen 10 hours 8 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

You must consider the production rate as per different crew sizes; 10 workers and x rollers might do the job in 8 hours or 80 manhours, but it is not the same as 40 workers and 2x rollers in 2 hours for same 80 manhours, it is not the same as 80 workers and 8x rollers pulling cables for 1 hour or 160 workers and 16x rollers for 1/2 hour.

That a woman can bear a child in 9 months it does not means 9 women can bear a child in 1 month. 

This is not how PMs manage their activities and crew composition at the jobsite.

We use our crew production records, our experience and for the few activities where there are no records we use industry references such as RS Means where production rates consider crew composition.  Reference books that only provide man-hours I consider a joke.  With very few exceptions modeling activity duration based on a fixed production rate is in error.  Use this functionality with caution. 

Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Cable pulling through a cable duct maybe too delicate to handle especially when length is in kilometers. So most likely it will be all manual with some rollers perhaps. Just use the reference book (production rates) as a guide, but there's nothing better than what you have actually experienced in real life.
Rafael Davila
User offline. Last seen 10 hours 8 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229

Do you use machines, or all work you do is without machines?

What will be the production rate to move dirt if by hand or if using an excavator.  What if the excavator used is replaced by another more productive?

Construction estimators do not rely on isolated man-hours production rate but instead consider the crew production rate.

Without few exceptions to adjust activity duration without taking into consideration the crew as a whole is in abominable horror.

Multi-resources and skills modeling can become handy when in need to allow the software to make such adjustments, otherwise you might be better off if using fixed composition crews along with their production rates as a team. 

Activity duration from Rafael Davila
Muhammad Bilal
User offline. Last seen 4 years 42 weeks ago. Offline
Joined: 9 Apr 2015
Posts: 14
Groups: None

Sir Trevor Rabey,

Thanks for your reply, During Scheduling in Primavera, We have to put estimated duration of each activities, thats why duration is to be calculated and i have fixed Duration/Units. but the confusion is that, manhour would be hours/unit or unit/hours? means we have to multiply it with the total quantity or have to divide with it? 

if manhour is Unit/Hour productivity then have to divide to get the duration...

For example: 

 

Buried Steel Duct 100x600 (4"x 24")

Unit of Time: "Hours";

Unit of Qty "Meter";

Manhour Factor: 2.16

If BOQ Quantity of Steel Duct is 800 Meter, So what would be the correct Answer? Number 1 or Number 2 ???

Number 1:

800 x 2.16 = 1728 Hours = 1728/10 (Working Hours) = 172.8 Days further Divided by Size of Crew to get the estimated duration.

Number 2:

800 / 2.16 = 370.3 Hours = 370.3/10 (Working Hours) = 37 Days further Divided by Size of Crew to get the estimated duration.

Kindly, Help me out to understand how can i use standard manhours (Productivity) to calculate the activity durations?

This is not straightforward. 

The crew may be complex and some resources may be used part time.

.

Trevor Rabey
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None

If you have the manhours, you also need the number of men. There is no need to convert manhours to duration. Just start with an estimate. Say you have 100 manhours/1000 metres of cable. Make a task, "install 1000 m of cable", estimate 40 (or 60 or 80, your initial estimate is not important) hours duration, assign two men, $100/hour at 100%, ie 8 hours per day. The work is 2 x 40 = 80 manhours, but your rate is 100 manhours/1000. You need more duration, about 5/4 or 1.25 times what you have now. Make duration 50 hours. Now you have 2 x 50 = 100 manhours. Then you also know the cost (because manhours is more or less the same as cost anyway) so 100 manhours x $100/manhour = $10000. Problem solved in one iteration.

Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
Simple but tricky question: Man-hour = OneMan/OneHour; Man-Day=OneMan/OneDay (not sure however, if how many hours in one day, as humans can never work 24 hours straight). I suggest to forget about standard references for production rates. Make your own production rates so that you will never forget.