Engineering Manhours relational to Procurement Manhours

19 replies [Last post]
William Rosborough
User offline. Last seen 18 years 9 weeks ago. Offline
Joined: 20 Jan 2006
Posts: 6
Hi folks,
Interested if anyone has any data/experience in the Oil/Gas industry pertaining to the relationship between Engineering manhours and Procurement manhours for a typcical EPC project.
thanks, Bill

Replies

Rafael Davila
User offline. Last seen 14 hours 35 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Ritesh Parakkal
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 9 Aug 2011
Posts: 4
Groups: None

Planning Manhours

Hi All ,

I dont see any reference to Planning Manhours / Productivity for different activities on the Planning Planet. Can anybody refer me to any Websites or links where i can refer to these for my Planning and Costing activities  for Oil & gas Projects like Plants , Refineries, Petrochemicals, Pipelines etc 

Regards

Ritesh

Ritesh Parakkal
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 9 Aug 2011
Posts: 4
Groups: None

What would be the Manhours required for Engineering of a Building ( Steel Structure + Sandwich Panel) of Size 49 Mts x 13 Mts X 4 Mts height . Engineering Manhours ?

 

Can i refer somewhere for this Information ?

Regards

Ritesh Parakkal

riteshparakkal@gmail.com 

Ritesh Parakkal
User offline. Last seen 1 year 43 weeks ago. Offline
Joined: 9 Aug 2011
Posts: 4
Groups: None

What would be the Manhours required for Engineering of a Building ( Steel Structure + Sandwich Panel) of Size 49 Mts x 13 Mts X 4 Mts height . Engineering Manhours ?

 

Can i refer somewhere for this Information ?

Regards

Ritesh Parakkal

riteshparakkal@gmail.com 

Jenny Ingco
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All,

I am working on Oil and Gas schedule and this my 1st time working on Manhours issue I use to work on Nonlaboer scheduls. I just need to know how I can calculate the Manhour I mean what formate I should use? And I appricate if someone wann take a look on my schedule and can help me to know whats the wrong data I using?

Thank you,

Nicole Bryan
User offline. Last seen 11 years 10 weeks ago. Offline
Joined: 5 Mar 2012
Posts: 7

hi,

i would appreciate if someone can help send me also the weighting know how ffor oil and gas, samples and data base on experience will be a great help. this is my email.. brynic717@yahoo.com.ph

thank u,

nicole

Jenny Ingco
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All,

I am facing same issue with my schedule which my manager asked me to review it for our clint and make some nots but the issue I don't know exactly what I should check? If someone interased I can send you the schedule and let me know...

Thank you,

Jenny Ingco
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All,

I am facing same issue with my schedule which my manager asked me to review it for our clint and make some nots but the issue I don't know exactly what I should check? If someone interased I can send you the schedule and let me know...

Thank you,

J Karthik Kumer
User offline. Last seen 12 years 18 weeks ago. Offline

Dear Mehdi Rashidi, sir,

 

 i also working in oil & gas (epc project), i also doubt have how to assign weight to engineering, procurement, construction, commissi etc... ,

kindly send me the data for my mail id : jk_jayaraman@yahoo.com

or otherwise i will be contact to your mail id sir,

even how to (what based on values assign this -manhour,cost)

i expect the your valuable replay 

Mehdi Rashidi Ala...
User offline. Last seen 5 years 36 weeks ago. Offline
Dear Ibrahim,
As you know, this weight depend on scope of project.
If you have any question about PM in Oil & Gas please contact with my email.

B/R
Mehdi
Norzul Ibrahim
User offline. Last seen 16 years 26 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
Dear Mehdi,

It’s interesting to notice such a big variation on the utilization/percentage of manhours especially for the construction i.e. 76% (my project) vs 45% (your project).

Perhaps it’s good if we could exchange information on this respect.

Thanks

norzul

Mehdi Rashidi Ala...
User offline. Last seen 5 years 36 weeks ago. Offline
Dear William,
I you want some information about know- how weighting oil& Gas Projects.please contact with me by email, mehdi.rashidi@engineer.com

Also, notice that my example is output from our project but for new calculation weights of project we need project scope of work.

Best Regards
Mehdi Rashidi
Norzul Ibrahim
User offline. Last seen 16 years 26 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
William,

The figure that I mentioned maybe applicable to our enviroments only. This may depend on kind of project, labor cost, type of contract, etc...

Thanks

norzul
William Rosborough
User offline. Last seen 18 years 9 weeks ago. Offline
Joined: 20 Jan 2006
Posts: 6
Mehdi Rashidi Alangeh,
Certainly appreciate you reply and advice.
Regards, Bill
Mehdi Rashidi Ala...
User offline. Last seen 5 years 36 weeks ago. Offline
Engineering manhours = 25%
Procurement = 20%
Construction = 45%
Commissioning = 10%

You notice that this weights based on size & type & scopw of work of project.
William Rosborough
User offline. Last seen 18 years 9 weeks ago. Offline
Joined: 20 Jan 2006
Posts: 6
Norzul,

Many thanks for this base information, exactly the feedback I was looking for.

regards, Bill
Norzul Ibrahim
User offline. Last seen 16 years 26 weeks ago. Offline
Joined: 17 Dec 2005
Posts: 165
I’m currently involve in a project (EPCC Type Contract)
1) Total estimated plan manhours = 1.7 million manhours
2) Engineering manhours = 1.3% (based on actual the engr manhours has doubled or tripled...)
3) Procurement management manhours = 4.7%
4) Construction workforce/management manhours = 76.0%
5) Commissioning workforce/management manhours = 8.0%
William Rosborough
User offline. Last seen 18 years 9 weeks ago. Offline
Joined: 20 Jan 2006
Posts: 6
Hatem,
Thanks for the interest, wondering if there is a relationship between the number of Engineering MHRs and the number of Procurement MHR’s documented anywhere based on an EPC project wherein Engineering and Procurement is done by the same organization.
thanks, Bill
Hatem Mahmoud
User offline. Last seen 2 years 8 weeks ago. Offline
Joined: 1 Nov 2004
Posts: 13
Hi William,

I didn`t get what exactly you want, you ask about the relative weight between engineering MHR`s & procurement MHR`s? or about other thing?