Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to reschedule??

2 replies [Last post]
Abdul Mehroof
User offline. Last seen 8 years 30 weeks ago. Offline
Joined: 11 Jul 2015
Posts: 2
Groups: None

Intially the project finish date was 30April 2016, Because of the Penalty milestone, dates have been prepon to Dec 2015..so how to fix this in p6???

Replies

And if your question is about P6 select appropriate discussion http://www.planningplanet.com/forums/oracle-primavera-pm6

Zoltan Palffy
User offline. Last seen 3 days 23 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

change the project must finish by date 

change the durations 

change logic 

ask for more money to accomplish the above