Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

MEP Sequence

3 replies [Last post]
Project Planner
User offline. Last seen 9 years 5 weeks ago. Offline
Joined: 16 Apr 2014
Posts: 4
Groups: None

I need the sequence of work and relationship for the following Electrical activities

Embedded Conduiting in the Floor Slab
Conduiting in Blockworks
Installation of Trunking
Install Cable Tray
Wiring for Lighting
Wiring for Power
Wiring for Fire Alarm
Wiring for Emergency Lighting System
Dressing & Termination of Fire Alarm
Wiring for IP CCTV
Dressing & Termination of Emergency Lighting
Wiring for SMATV System
Dressing & Termination of SMATV
Wiring for Structured Cabling
Wirng for BMS
Dressing & Termination of Structured Cabling
Dressing & Termination of BMS
Dressing & Termination of CCTV
Uninteruptable Power Supply (UPS)
Central Battery System
Installation of BMS

Thanks in advance

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

conduit, wire then terminations

in slab would be first

then the highest component in the ceiling 

then any in-wall work 

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

conduit, wire then terminations

in slab would be first

then the highest component in the ceiling 

then any in-wall work 

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Project

That is too much detail.

You need to split the MEP into 3 tasks - Ducting > Pipework> Containment.

These are place vertically in risers and horizontally in ceiling zones and / or floor zones.

Cables are placed in the containment after weather tight conditions.

IT cables have seperate containment and must not be placed close to HV / LV cables.

Best regards

Mike Testro