Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Updating P6 Programme for remeasured Contract

2 replies [Last post]
Celso Paman
User offline. Last seen 3 years 45 weeks ago. Offline
Joined: 15 Jan 2010
Posts: 5

Dear PP Experts,

We have a road project and it is under a remeasured contract. There are differences between BOQ Quantities (loaded in the programme) and the actual quantities such as volume of excavated materials, etc. This means that the activities in the P6 schedule loaded with the BOQ quantities will not represent the correct planned progress.

Sample scenario is this.

Planned: Activity 1 has 1000 cum of excavated material

Actual: Activity 1 has 1300 cum of excavated material (100% done)

Therefore: the progress is only for 1000 cum and not on 1300 cum.

Question is, how to reflect the correct appearance (might be addition or subtraction from the original scope) of the updated program. I would very much appreciate it if you could give guidance for calculating progress and producing curves on the remeasured contract.

Appreciate your time an effort.

Regards,

Celso

Replies

Rafael Davila
User offline. Last seen 8 hours 37 min ago. Offline
Joined: 1 Mar 2004
Posts: 5229
Dieter Wambach
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Hi OL

Was it an official remeasurement agreed by both sides? Was then any reason why it wasn't re-baselined as well?

This is management's not planners' decision.

Basically you have two alternatives:

1. Build a new plan and make this the new baseline. But you'll have a rupture in all s-curves and reports, which often must be explained. P6 can examine both BL simultaneously.

2. Leave the old BL, then you can better explain variances (e.g. EOT claims, ...)

Which alternative to choose will depend on the current situation. So you'll make your proposal.

During my first lesson at University in planning I learnt that it is just by chance if reality meets plan or forecast. Variances do happen.

Good planning!

Dieter