Dear PP Experts,
We have a road project and it is under a remeasured contract. There are differences between BOQ Quantities (loaded in the programme) and the actual quantities such as volume of excavated materials, etc. This means that the activities in the P6 schedule loaded with the BOQ quantities will not represent the correct planned progress.
Sample scenario is this.
Planned: Activity 1 has 1000 cum of excavated material
Actual: Activity 1 has 1300 cum of excavated material (100% done)
Therefore: the progress is only for 1000 cum and not on 1300 cum.
Question is, how to reflect the correct appearance (might be addition or subtraction from the original scope) of the updated program. I would very much appreciate it if you could give guidance for calculating progress and producing curves on the remeasured contract.
Appreciate your time an effort.
Regards,
Celso