Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

275kV/400kV Cable Laying Norms

1 reply [Last post]
John Sims
User offline. Last seen 10 years 28 weeks ago. Offline
Joined: 2 Jun 2011
Posts: 49
Groups: None

Dear Planners,

Does anybody have any norms on durations that would be useful for laying 275kV/400kV cables?

I am planning a project that requires this work.

 

Thanks John

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi John

Above or below ground?

Inside or outside a building?

What length?

Best regards

Mike T.