Resource Overallocation.

4 replies [Last post]
AB Timo
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hi Guys,

I added a resource "Tile Fixer" to an activity using following steps.

1 .In Resource window added Resource "tile Fixer.Assigned it calender (8hrz/Day),entered Price/Unit.

2 .In activity window click on Resource "Tab",selected the Resource "Tile Fixer" and Entered "16h/Day" in "Remaining Units" Column (Because 2 Tile Fixers were required to work each day for 8 Hrz).

After That when I see the "Resource Usage Profile" window it is showing "Overallocation" of 8 Hrz each day.Please tell me that is it correct to enter 16h/Day or i should enter 8Hrz/ Day two times???

 

Best Regards,

Replies

D Artagnan
User offline. Last seen 2 years 7 weeks ago. Offline
Joined: 19 Sep 2008
Posts: 207

In the resource window the default, perhaps, that you have is, for the 'max unit/day' is 8/d. Make it 16/d then, it will even out.

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Faiz

I can't answer for P6 but in Asta Powerproject you enter the number of hours that the tiling task will require to complete and then the number of tilers that are available.

The resource modelling software then calculates the duration - I assume that P6 has a similar system.

Best regards

Mike Testro

AB Timo
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

Hey Mike,

Thanks for the reply.But Consider an activity where 20 Labors and 10Non Labor units are required.Even these number can further increase.Then Assigning them Separately will be such a waste of time.Is there any short way to assign multiple resources at a time?? What ractice should be followed??

 

Best Regards

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Faiz

You should enter two tilers for 8 hrs a day.

Best regards

Mike Testro