UPDATING THE PROGRESS

1 reply [Last post]
AB Timo
User offline. Last seen 9 years 6 weeks ago. Offline
Joined: 22 Jun 2011
Posts: 108
Groups: None

HI Gentlemen,

I have been updating the progress in primavers  version 6, by using Duration as % complete type.But i have also heard that one should use Physical as % complete type...I then used physical but the results were the same.Can someone tell me that what is the difference in using these two?????

 

Regards,

Replies

Hilal Hallani
User offline. Last seen 12 years 6 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 16
Groups: GPC Qatar

Physical % complete is entered by the user and it implies that when percent complete would not be an accurate measure of real work performed or remaining. Where % complete can be entered by the user or the programme, this is not a real measure.

Physical % complete is preferred over % complete in construction projects where speed of doing the work in activities does not remain same during the activity duration.