(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

BEST TO UPDATE

5 replies [Last post]
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
HI, THIS THE BEST WAY TO UPDATE YOUR BASE LINE BY PRIMVERA UPDATE GO TO TOOL AND SELECT UPDATE PROGRESS OR PRESS CTRL+F9. SET A DATA DATE AS YOU EQUIRED.

THEN PUT THIS AS A TARGET ONE AND YOUR SCHEDULE WHICH YOU WANT TO UPDATE PUT AS A TARGET TWO

IN THAT YOU CAN COMPARE YOUR BASE LINE VS CURRENT SCHEDULE.


THANKS

Replies

Shahzad Sikandar
User offline. Last seen 5 years 45 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
ok got you.

Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
SORRY...DEAR

I FORGET TO EXPLAIN YOU ..UDATE FILE NOT A BASE LINE..IT IS DUMMY OF BASLINE...WHICH I AM USE TO UPDATE....BY PRIMAVERA...

TO GET A PLANNED % PROGRESS AS ...I DID NOT MENTION COST OR....

CHEER

Shahzad Sikandar
User offline. Last seen 5 years 45 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
didnt get you sorry,

i can do the same in current project, as it is compared against the baseline, as i update current schedule, i get earned value for this in terms of units or cost?

why would i have to update baseline in order to get planned % progress.... are you talking about PLanned value? (budgted cost of work scheduled-BCWS)???

Please light more
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi,Shahzad



This is the one way to obtained a Planned % Progress

based on duration.

I did this ...for my current project..which is very helpfull for Invoicess.

you are right this is only for P3.1 option.

I hope ..it would be clear...

Thanks
Shahzad Sikandar
User offline. Last seen 5 years 45 weeks ago. Offline
Joined: 1 Feb 2006
Posts: 67
Groups: None
Shahzad

I dont really get you,,why press Ctrl + F9 ,,it never works anyway in P6/P5..

Why do you really need to updates the baseline,,,its a frozen entity, and you only reschedule current programme,,,

please explain to me what you are trying to say.

may be i am missing something?

thanks
TC