Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

The Exact Definition of Open End Activity

6 replies [Last post]
Mai Tawfeq
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 4 Mar 2010
Posts: 96

Dears:

 

A discussing was going on in regard of exact definition of open end activity.

Some said that open end activity, the activity without successor and others said that open end activity which is belong and come under open end track or path even the activity has predecessors or successor but the end of track where it belongs is opened with no links to project completion date.

 

So now my dear I need some expertise opinions.

 

Thanks. 

Replies

Gehan Mahmoud
User offline. Last seen 8 years 16 weeks ago. Offline

Dear Mai,

Please i need your advice to filter those items with relationships SS OR FF. i saw them in Gantt chart as open ended items but in Log file those items did not appear. I need your guide to filter those items.

Regards,

Tanveer Ahmad Niazi
User offline. Last seen 6 years 4 weeks ago. Offline
Joined: 15 Dec 2005
Posts: 151
Groups: GPC Qatar

Hi Planners,

In my opinion the term “open end” is a dual relation. One with the software term and the other with the planning term or perception. In the first one means as Gary Whitehead stated. The other one means that the questioner already mentioned that it’s an activity at the end of the track or chain that has no successor and has no effect on the project finish date.I would rather suggest not to mix the both.

Andrew Owenson
User offline. Last seen 1 year 1 day ago. Offline
Joined: 18 Jun 2008
Posts: 68
Groups: None

Guys

 

I would agree with Gary.... I remember quite a few years ago being taken on by Balfour Beatty to sort out a programme in Artemis I think. the previous planner had jacked and the programme literally wouldnt run because it had open ends, ie missing successors or predecessors. The software was written so you could not cheat like you can in todays world. Took me ages to resolve.

ps SS link does not count.

 

 

Andrew

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

My understanding of open ended is that either

a) no other activity is driving the activity (open at the front end)

b) no other activity is driven by the activity (open at the back end)

 

Certainly this is the same definition Primavera use. I know Primavera are not the font of all knowledge, but theirs is the only written definition of open-ended I have come across.

 

I agree that having only ss sucessors is bad practise, but I don't think it is open ended.

Mai Tawfeq
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 4 Mar 2010
Posts: 96

   hi Gary:

I think this is a floated Activity, not opened end.

When activity link to other predecessor and successor ss relationship type it can: opened end (Finish has no successors)

i have similar I would show u but unfortunately i could not load the file .

 

regards 

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Open end activity means an activity with either no sucessor or no predecesor.