Activities starting at the end of the shift

2 replies [Last post]
Kevin Rayner
User offline. Last seen 2 years 33 weeks ago. Offline
Joined: 9 Jan 2009
Posts: 17
Groups: None

A couple on months ago somebody at work corrupted the most used calendar in the database. This has been rectified but I am now finding activities starting an the end of a shift rather than the start of the shift on the next day.

I cant see why if the shift ends at 16.00 why the successor with an FS link is starting at 16.00 and not 08.00 the next day.

Replies

Zoltan Palffy
User offline. Last seen 19 weeks 5 days ago. Offline
Joined: 13 Jul 2009
Posts: 3088
Groups: None

make sure that the activities are assigned to the correct calendar 

Kevin Rayner
User offline. Last seen 2 years 33 weeks ago. Offline
Joined: 9 Jan 2009
Posts: 17
Groups: None

Fixed now. the calendar had been incorrectly amended.