A couple on months ago somebody at work corrupted the most used calendar in the database. This has been rectified but I am now finding activities starting an the end of a shift rather than the start of the shift on the next day.
I cant see why if the shift ends at 16.00 why the successor with an FS link is starting at 16.00 and not 08.00 the next day.